Strona 1 - CENTURION

Latest Revision: 27.01.2006Document Ref.: 1114.D.01.0001_25INSTALLATIONMANUALCENTURIONTHE AUTOMATIC CHOICEA10

Strona 2

Page 10Duty Cycle CurvesCalculating the duty cycleThe duty cycle is the ratio of the actual operating time to the total time (opening plus closing plu

Strona 3 - WARNINGS FOR THE INSTALLER

Page 11Figure 3 Duty Cycle CurvesA10 ENDURANCE Duty Cycle CurveAll speed combinations70809010020 30 40 50 60 70 80 90Time (Minutes)Duty Cycle (%)4m 50

Strona 4 - Fast TrackFast Track

The actual components supplied may vary depending on the model purchased.Product IdentificationProduct IdentificationFigure 4 Product IdentificationPa

Strona 5

Required Tools & EquipmentRequired Tools & EquipmentMasonry Bits - 6mm20mm (For sites with rawlbolted foundation plates)Steel Bits 8,5mm/5,0mm

Strona 6 - Lightning Protection

Page 14Install the gate operator only if:1. It will not pose a hazard to the public.2. There is sufficient clearance to a roadway and/or public thorou

Strona 7 - Theft Protection

Page 15End StopsØ16mmhHFIT END-STOPS (1) CAPABLE OF STOPPING THE GATE MOVINGAT RATED SPEED.MAKE H≥hTO ENSURE GATE WILL NOT JUMP OVER END-STOP. 11F

Strona 8 - Specifications

- Guide rollers must ensure that the gate is held vertically.- Fit suitable anti-lift brackets . The gap should be <5mm to ensure

Strona 9 - 1000kg (Sprint speed) 600kg

- The Centurion warranty will be void if the pull force , and/or gate mass, exceeds the operator specification (see table below)6Starting & R

Strona 10 - Duty Cycle Curves

Page 18Cabling RequirementsCabling Requirements1To dwellingi sMa ni l t rso a ochswit251. 220V AC mains cable via mains isolator 5. Infrared beams or

Strona 11 - All speed combinations

Side ClearancePage 19Foundation Plate InstallationRack/Axle Clearance5mmLower cover is approximately 5mm wider than chassis each side. Allow additiona

Strona 12 - Not fitted to BASIC model

Page 2Centurion Systems (Pty) Ltd. reserves the right to make changes to the products described in this manual without notice and withou

Strona 13 - 3.5mm Flat

Foundation Plate Installation - option 1(Bolted down to existing concrete block)!The LH concrete anchor may need to be broken off in order to clear i

Strona 14

Page 21!!Use self locking or crimping pliers to bend the anchor tips 12 to the horizontal plane.!Make sure the M10 bolts 13 which secure the gea

Strona 15 - End Stops

Page 22LubricationThe internal wormshaft/wormwheel gearset of the A10 is lubricated by means of an oil bath.Important InformationImportant Information

Strona 16 - Anti Lift Brackets

Gearbox Mounting Down DetailsPage 23Operator InstallationOperator InstallationFigure 16 Gearbox Mounting Down DetailsAssemble nut, springwasher, and l

Strona 17 - Starting & Running Forces

lRaise gearbox by an additional 3mm.lPut gearbox into manual mode (see page 41)lMesh rack and pinion fully and mount rack. Slide gate backwa

Strona 18 - To dwelling

1617±300 mmPage 25Figure 18 Mounting Rack

Strona 19 - Side Clearance

Page 26Chain Drive Installation (Optional)BARemove all four captive nuts from gearbox as shown.Assemble as shownFigure 19 Chain Drive Installation

Strona 20 - Use steel rack

Page 27- Weld rear anchor plate onto gate such that centre line of tensioner pin is in line with top of the shaft on the idler pulley

Strona 21 - 20mm conduits

Page 28Origin Marker MountingFigure 21 Origin Marker Mounting13-20mmB1819CGREATER THAN 500mmAMOUNTING CONFIGURATIONFOR STEEL RACKORIGIN MARKERBRACKETW

Strona 22 - Lubrication

- With the gate in the CLOSED position, mount the origin marker 18 a minimum of 500mm from the origin sensor 19 . (See Fig. 21 isometric view A or

Strona 23 - Gearbox Mounting Down Details

Important Safety InstructionsImportant Safety InstructionsTo ensure the safety of people, it is important that you read all the following instructions

Strona 24 - Joining/Mounting Rack

Electrical Set-upElectrical Set-upPage 30WARNING1. Always check that the circuit breaker in the electrical panel is in the OFF position, and that all

Strona 25 - Figure 18 Mounting Rack

Page 31“Flip Out” Controller MountingController enclosure verticalController enclosure raisedController enclosure proppedFigure 22 Controller Mounting

Strona 26 - Assemble as

Page 3211. The gate will then open at normal speed until the magnet passes the origin, and then slowly open until it hits the open end stop.12. The ga

Strona 27 - >100mm

Page 33Get Into Programming Mode (Exactly the same as for limits setup)18. Fit the SET link jumper to the SET pins as shown in Figure 23.19.(See Faul

Strona 28 - Origin Marker Mounting

Press and hold the TEST button while monitoring the STATUS light. The STATUS light will flash the same as for selecting a Feature. (See Step 21)

Strona 29

Page 35Example 2 (continued):At this moment release the TEST button to give a COUNT value of 10. This sets the auto-close timer to 10 seconds.L2 will

Strona 30 - Programming the gate limits

Page 36automatically be turned on when condominium mode is selected. It is only the auto-close signal, which can close a gate in condominium mode. I

Strona 31 - Controller enclosure propped

Page 37!It can be turned on for the preset timed period, by the application of a short impulse between the SET terminal and COM.!It can be turned ON p

Strona 32 - (Optional)

Page 38closing direction.Sprint Mode (FEATURE 13-STATUS, FEATURE 14-STATUS)It is possible to select 4 different gate speeds. Feature 13 selects the op

Strona 33

Page 39Procedure to Programme Controller Back to Factory Default SettingsProcedure to Programme Controller Back to Factory Default Settings1. Apply po

Strona 34

These abbreviated instructions are for the experienced installer who needs a checklist to get a standard installation up and running in the minimum of

Strona 35 - Controller Features

Page 40Receiver InstallationReceiver InstallationFigure 24 Receiver InstallationNOTE: Although a space is provided for locating a radio receiver withi

Strona 36 - Deadman Control (FEATURE 4-6)

A BACPage 41Manual Release OperationManual Release OperationManual release handle in closed position.Pull manual release handle down to enable manual

Strona 37

Page 42Manual Release LatchingManual Release LatchingIn the event of power failure, or product malfunction, it may be required to lock the cover in pl

Strona 38

A BTheft Resistant Cage FittingTheft Resistant Cage FittingDCPage 43

Strona 39

Page 44E F

Strona 40

Figure 25 CP201 Trigger ConnectionsPage 45CP201 Trigger ConnectionsCP201 Trigger ConnectionsNEG NEG NEG+12V+12V/24V+12V/24VPUSHBUTTONFOR SWITCHINGPILL

Strona 41

Page 46A10 Cable RoutingA10 Cable RoutingFigure 26 A10 Cable RoutingTIO ALFROM OP NRDC CONVE TERNA SIG L CAB ELTO CONTROLLERPTO I LARLIL GHTSFROM C

Strona 42

Page 47Figure 27 A10 Cable InterconnectionsA10 Cable InterconnectionsA10 Cable InterconnectionsP L COUR E YILAR / T SL HT (P TE L RIG O NTIA F EE)M

Strona 43

NAMECOLOUR ON OFF REMARKSTRGRedSignal presentSignal presentSignal presentSignal presentNo signalNo signalNo signalNo signalN/AIRBGreenSafeties clearSa

Strona 44

FEATUREDESCRIPTIONAuto-closeAuto-close TimeGate Limit Settings-See detailed instructions on page 30123STATUS or COUNTDESCRIPTION-ON15 seconds (Defaul

Strona 45 - RADIO RECEIVER

Connect all wiring: Page 30Get into programming mode: Page 30Fit the SET link.Briefly depress the reset button.Set the gate limits: Page 30Press and h

Strona 46 - Figure 26 A10 Cable Routing

FEATUREDESCRIPTIONSTATUS or COUNTDESCRIPTIONFEATURENUMBERCOUNTVALUEPage 50Table 2 continued Controller Functions Menus and SubmenusSTATUSVALUEStandard

Strona 47

Page 51Installation DetailsInstallation Date:Installer's Name:Installer's Address:Installation Checked By:Installer's Telephone Number:

Strona 48 - COLOUR ON OFF REMARKS

CENTURIONTHE AUTOMATIC CHOICE CENTURION SYSTEMS (PTY) LTD HEAD OFFICE:TEL: +27 (0)11 699-2400, FAX: +27 (0)11 704-3412 or 462-6669 148 EPSOM AVENUE, N

Strona 49 - STATUS or COUNT

General DescriptionGeneral DescriptionPage 6The A10 is a heavy duty sliding gate operator designed to open and close sliding gates.In cases where chai

Strona 50

Page 7Overall DimensionsTheft ProtectionFigure 1 Overall DimensionsAll dimensions shown in millimetres384300340 (Theft resistant cage)23470While care

Strona 51 - Installation Details

Page 8SPECIFICATIONSDC CONVERTER SPECIFICATIONSPower SupplyMaximum Absorbed CurrentMotor VoltageOutput PinionStarting ThrustRated ThrustOperating Spee

Strona 52

Page 9A10 ENDURANCEA10 HEAVY WEIGHT220V +/- 10%, 50Hz - 1 Phase 220V +/- 10%, 50Hz - 1 Phase6A 6A220V 3 Phase 220V 3 Phase20 Tooth Mod 4 17 Tooth Mod